Example 1 · Residential

A $1 million home improvement, and a Cobra

Kitchen, primary suite, impact openings and the systems behind them, in an occupied waterfront residence. The owner applies a Shelby-licensed continuation Cobra.

Palm Beach County · occupied residence · no change to the footprint

Schedule of valuesScheduled value
Design coordination, engineering and permits$50,000
Demolition and protection of finished areas$37,500
Structural and framing modifications$75,000
Impact-rated windows and doors$150,000
Mechanical, electrical and plumbing$175,000
Kitchen: cabinetry, stone and appliances$200,000
Primary suite and bath$112,500
Flooring, millwork and finishes$137,500
General conditions$62,500
Contract sum$1,000,000

Asset applied

Asset
Shelby-licensed continuation Cobra
Agreed purchase price
$75,000
Secured
Purchase agreement executed with the construction agreement; purchaser noted as lienholder on the Florida title until closing.
Closes
Rough-in, credited against that pay application.

Billing

Pay applicationWork completedRetainageAmount dueAsset creditCash
Mobilization and demolition$150,000($15,000)$135,000—$135,000
Rough-in inspections passed$300,000($30,000)$270,000$75,000$195,000
Finishes installed$300,000($30,000)$270,000—$270,000
Substantial completion$150,000($15,000)$135,000—$135,000
Retainage reduction at 90% complete—$45,000$45,000—$45,000
Final completion$100,000$45,000$145,000—$145,000
Total$1,000,000—$1,000,000$75,000$925,000

10% retainage until 90% complete; half released at 90%, the balance at final completion.

  • Price agreed at signing; independent inspection before the milestone.
  • The car changes hands at rough-in. Retainage follows under the construction agreement, lien rights intact.

Example 2 · Land

Seven rural acres, from raw land to an entitled site

Seven acres under a rural land-use designation, intended for a residence and a collector’s barn. The economics are governed less by construction than by entitlement: land use, wetlands, species and utilities.

Rural future land use · ≈0.5 acre jurisdictional wetland · well and septic · county-road frontage

Entitlement sequence

  1. 1Due diligence

    30–60 days

    • Boundary, topographic and tree survey; title commitment
    • Phase I ESA
    • Wetland delineation; jurisdictional determination
    • Listed-species survey (gopher tortoise and others)
    • Geotechnical borings; percolation
    • Flood zone, access, zoning verification, utility availability
  2. 2Land use and zoning

    4–12 months

    • Pre-application conference
    • Small-scale plan amendment, where use or density requires it
    • Rezoning, conditional use or PUD; public hearings
    • Traffic and school concurrency
  3. 3Environmental permitting

    6–12 months, in parallel

    • Water management district ERP (stormwater and wetlands)
    • Federal Section 404 authorization where wetland impacts are proposed
    • Mitigation-bank credits (UMAM)
    • Gopher tortoise relocation; tree and vegetation permits
  4. 4Site plan, plat and utilities

    3–6 months

    • Engineering: grading, drainage, access
    • DOH septic and well permits, or utility agreements
    • Plat and improvement bonding, if divided
  5. 5Site development

    4–6 months

    • Clearing, grading and fill to elevation
    • Stormwater management
    • Access, culverts and fire access
    • Well, septic and power
Schedule of valuesScheduled value
Due diligence: survey, title, ESA, wetlands, species, geotechnical$66,250
Land planning, land-use counsel and traffic$90,000
Civil engineering through permitting$106,250
Application, hearing and permit fees$18,750
Environmental permitting$43,750
Wetland mitigation credits$93,750
Gopher tortoise relocation; tree mitigation$37,500
Clearing, grading and fill$150,000
Stormwater management$112,500
Access, culverts and fire access$168,750
Well, septic and power$118,750
General conditions and improvement bonds$56,250
Contingency for agency conditions$100,000
Contract sum$1,162,500

Schedule

Twelve to twenty-four months from diligence to a permitted, developed site, governed by hearings and environmental permits. Vertical construction follows under its own agreement.

  • Wetland boundaries, species findings and hearing outcomes move cost and schedule more than construction does. They are resolved before the building budget is fixed.
  • Alternatively, the parcel itself may be the asset, applied toward a project elsewhere at a price agreed on the land as it stands, unentitled.

Example 3 · Commercial

A 25,000-square-foot flex warehouse on the owner’s commercial site

A tilt-wall flex building with 3,000 square feet of office on the owner’s commercially zoned site. The owner applies a Porsche 964 RS.

≈2.5 acres · commercial zoning · utilities at the property line · site acquisition, where needed, through Barefoot Realty (affiliation disclosed)

Schedule of valuesScheduled value
Architecture and engineering$225,000
Permits and impact fees$275,000
Site work: grading, stormwater, paving, utilities$1,125,000
Building shell: slab, tilt-wall, roof, storefront, dock doors$2,968,750
Office build-out, 3,000 sq ft$450,000
Fire sprinkler and alarm$218,750
Shell mechanical, electrical and plumbing$312,500
Landscape and irrigation$112,500
General conditions$275,000
Contingency$300,000
Contract sum$6,262,500

Asset applied

Asset
Porsche 964 RS
Agreed purchase price
$300,000
Secured
Purchase agreement executed with the construction agreement; lienholder noted on title, or the car held in third-party storage until closing.
Closes
Dry-in of the shell, credited against that pay application.

Billing

Pay applicationWork completedRetainageAmount dueAsset creditCash
Site work and slab$1,565,625($156,563)$1,409,062—$1,409,062
Shell erected and dried in$1,878,750($187,875)$1,690,875$300,000$1,390,875
MEP, sprinkler and office build-out$1,565,625($156,563)$1,409,062—$1,409,062
Substantial completion and CO$626,250($62,625)$563,625—$563,625
Retainage reduction at 90% complete—$281,813$281,813—$281,813
Final completion$626,250$281,813$908,063—$908,063
Total$6,262,500—$6,262,500$300,000$5,962,500

10% retainage until 90% complete; half released at 90%, the balance at final completion.

  • Same sequence as a residence: price agreed and secured at signing, closing at dry-in, retainage afterward.

Example 4 · Waterfront rebuild

A teardown past the 50% threshold, rebuilt as a luxury spec.

A 1970s house on the Intracoastal, where any meaningful renovation would exceed half the structure’s value and trigger a full rebuild to current flood standards. Rather than renovate into that constraint, the owner contributes the lot, Hoadley Construction builds a 6,000-square-foot residence at cost, Barefoot Realty lists and sells it, and the net profit is split equally.

Palm Beach County · 100 ft of frontage · rebuilt to current flood elevation · new seawall and dock

Structure

Owner
Contributes the lot at an agreed value of $3,500,000 and funds construction at cost.
Hoadley Construction
Builds at the cost of the work, general conditions included, billed monthly with standard retainage. No fee; its compensation is the profit participation.
Barefoot Realty
Retained as exclusive listing broker; earns the listing and sale commission. The affiliation is disclosed in writing.
At sale
Commission and closing costs first, then the owner’s capital returned in full, then net profit divided equally.
Security
The participation is recorded against the property. Pricing, timing and the owner’s option to keep the house at an appraised buyout are fixed at signing.

Cost of the work

Design, engineering and permits$300,000
Demolition and site preparation$120,000
Foundation and elevation to current flood standard$420,000
Structure and envelope: impact openings, roofing$1,650,000
Mechanical, electrical, plumbing and smart-home systems$720,000
Interiors: kitchen, baths, millwork and finishes$1,300,000
Seawall, dock and lift$380,000
Pool, hardscape and landscape$420,000
General conditions: supervision, insurance, site$380,000
Cost of the work, at cost$5,690,000

At sale: $13,000,000

Sale price$13,000,000
Listing and sale commission: Barefoot Realty & Investments (5%)($650,000)
Documentary stamps, title and closing($156,000)
Return of owner capital: lot, at the agreed value($3,500,000)
Return of owner capital: cost of the work($5,690,000)
Return of owner capital: carry (taxes, insurance, utilities)($200,000)
Net profit$2,804,000
Owner, 50%$1,402,000
Hoadley Construction, 50%$1,402,000

Sensitivity

Sale priceNet profitOwnerHoadley
$11,500,000$1,397,000$698,500$698,500
$13,000,000$2,804,000$1,402,000$1,402,000
$14,500,000$4,211,000$2,105,500$2,105,500

Break-even sale price: about $10,020,000. The owner’s capital of $9,390,000 comes back before any profit is divided, and the cost of the work has already been paid as it was built.

  • The construction company is paid at cost throughout; its profit is earned at sale, alongside the owner’s.
  • If the owner elects to keep the house, Hoadley Construction’s share is purchased at an independent appraisal under the same waterfall.

Illustrative only. These are not offers, estimates or quotes; budgets, schedules, entitlement outcomes and asset values vary by property, jurisdiction and market.

Begin a submissionHoadley Construction, LLC · Florida Certified General Contractor · CGC 1518691